Components and standards

What goes into a shelter, part by part: what each component does, the standard it is built or tested to, how long it lasts and how long it takes to get. Then the standards the rest of the world uses, and how long a build takes.

Who checks what, and how often
Six of the main shelter components Line drawings of a blast door with a locking wheel, an NBC air filter, a blast valve, a battery bank, a water store and a sump pump in its pit. Blast door NBC filter Blast valve Battery bank Water store Sump pumps

Structure

The shell that carries earth, resists blast and keeps water out.

Reinforced concrete shell

Walls 300–600 mm and roof slabs 400–750 mm of reinforced concrete, designed to carry earth cover, the collapse of structures above and blast overpressure.

Standard
IS 456, IS 13920 (ductile detailing), IS 1893 (seismic), IS 4991 (blast)
Life
Designed for 50+ years
Checks
Visual inspection for cracks and damp each year

Earth cover

1 to 3 metres of compacted fill over the roof. The cheapest and most effective radiation shield there is.

Standard
Compaction tested in layers during backfill
Life
Permanent
Checks
Settlement and drainage after each monsoon

Waterproofing system

Low-permeability concrete, external membranes, water-stops at every joint and sealed pipe sleeves. The system is chosen from the groundwater investigation.

Standard
IS 3370 principles for water-retaining concrete
Life
Membranes typically 20+ years
Checks
Sump levels and damp patches after monsoon

Sumps and twin pumps

Collect any water that reaches the structure and pump it out, on shelter power, with a standby pump.

Standard
Sized from site groundwater data
Life
Pumps 5–10 years
Checks
Test run every quarter

Anti-termite treatment

Soil treatment around the structure before backfill.

Standard
IS 6313
Life
Varies by treatment
Checks
Annual inspection

Doors and exits

Every opening is a weak point for blast, radiation and gas, so each one is engineered.

Blast door

A steel door in a steel frame cast into the concrete, rated to the shelter's design overpressure, with gas-tight seals and locking from inside.

Standard
Rated and tested to the shelter's blast class (1 to 3 bar+)
Lead time
8–16 weeks, made to order
Checks
Seal and hinge service each year

Gas-tight inner door

Creates the airlock with the blast door, so people can enter and decontaminate without breaking the seal.

Standard
Air-tightness tested at commissioning
Lead time
6–12 weeks
Checks
Seal inspection each year

Escape hatch and shaft

A second way out, placed outside any collapse zone, openable from inside and outside, concealed at the surface.

Standard
Same blast class as the main entry
Lead time
8–12 weeks
Checks
Opened in every drill

Shielded entry passage

Entries that turn at right angles so there is no straight path for radiation, often with earth cover over the passage.

Standard
Designed into the structure
Life
Permanent
Checks
Kept clear of storage

Air

The system that decides how long a shelter can stay sealed.

NBC ventilation unit

Draws outside air through filters and pushes it into the shelter. Electric, with a hand crank for power failures.

Standard
Units type-tested for shelter use, such as Swiss-approved shelter ventilators
Lead time
8–16 weeks, often imported
Checks
Run monthly, service each year

HEPA particle filter

Captures fallout dust, smoke, PM2.5 and biological particles. H13 captures at least 99.95% of the most penetrating particle size; H14 at least 99.995%.

Standard
EN 1822 / ISO 29463 filter classes
Life
Replaced on schedule, and after any use in contaminated air
Checks
Pressure drop each year

Gas filter (activated carbon)

Adsorbs chemical agents and many toxic gases. Kept sealed until needed.

Standard
Military and civil protection CBRN filter specifications
Life
Per manufacturer's shelf life; replaced after any exposure
Checks
Seal and date check each year

Blast valves

Fitted on every air intake and exhaust. They close in milliseconds when a pressure wave arrives, then reopen.

Standard
Shock-tested to the shelter's blast class
Lead time
8–12 weeks
Checks
Movement test each year

Overpressure valves

Hold the shelter slightly above outside pressure so any leak flows outward.

Standard
Verified by pressure test at commissioning
Lead time
6–10 weeks
Checks
Gauge reading in every drill

CO₂ scrubber and oxygen reserve

For recirculation mode when outside air is unusable, such as during nearby fires. Removes exhaled carbon dioxide; larger classes add oxygen reserve.

Standard
Sized to occupancy and hours of sealed operation
Life
Absorbent replaced by date or after use
Checks
Stock and date check each year

Monitoring

You cannot see radiation or smell carbon monoxide. Instruments do the noticing.

Radiation meters

A survey meter for dose rate inside and outside, plus personal dosimeters. They decide when it is safe to leave.

Standard
Calibrated instruments with certificates
Life
Many years with care
Checks
Calibration as the maker specifies, typically yearly

CO₂, CO and O₂ sensors

Alarm before air quality becomes dangerous. Carbon monoxide alarms are standard in every shelter.

Standard
Certified gas detectors
Life
Sensors typically 5–10 years
Checks
Test every drill, replace by date

Pressure, temperature and humidity

Confirms the overpressure is holding and the cooling is keeping up.

Standard
Read on a single panel
Life
5–10 years
Checks
Logged in drills

Readiness monitoring

Optional remote alerts for water ingress, battery state and temperature, so faults are fixed long before an emergency.

Standard
Encrypted, minimal data
Life
Per device
Checks
Monthly status report

Power and cooling

In India, cooling is life support, so power is designed around it.

Battery storage

Lithium iron phosphate batteries take over instantly when the grid fails and carry the shelter for 48 hours or more on their own.

Standard
Certified cells and battery management, fire-rated enclosure
Life
Typically 10–15 years
Checks
State of health each quarter

Inverter and charge control

Converts and manages power from batteries, solar and generator, and sheds loads in priority order.

Standard
Certified to Indian electrical standards
Life
10+ years
Checks
Annual service

Solar array

Concealed panels, or panels stored inside and deployed after an event.

Standard
BIS-certified modules
Life
25+ years
Checks
Clean and test each year

Diesel generator and fuel

In a vented enclosure, with exhaust well away from the air intake and stabilised fuel.

Standard
Emission-compliant sets; fuel stored to safety rules
Life
Many years with servicing; fuel rotated
Checks
Run under load monthly

Cooling and dehumidification

Inverter cooling sized for full occupancy, with standby units on larger classes, and dehumidifiers to stop mould.

Standard
Sized to about 100 W of body heat per person plus equipment
Life
10–15 years
Checks
Service before each summer

Water and sanitation

Stored water

Food-grade tanks inside the protected envelope, at least 4 litres per person per day plus reserve.

Standard
Food-grade materials; water to IS 10500
Life
Tanks 15+ years
Checks
Water rotated every 6–12 months

Purification

RO and UV purification, plus gravity filters that need no power.

Standard
Output tested against IS 10500
Life
Cartridges by schedule
Checks
Cartridge change each year

Protected borewell

For Estate and remote shelters, a well head inside or beside the protected envelope.

Standard
Subject to local groundwater rules
Life
Long term
Checks
Water quality test each year

Toilets and holding tank

Chemical toilets, or flushing toilets into a sealed tank with manual pump-out.

Standard
Sized to occupancy and days sealed
Life
15+ years
Checks
Tested in drills

Backflow valves

On every drain, so a flooded or contaminated sewer cannot become a way in.

Standard
Fitted to all outgoing lines
Life
10+ years
Checks
Annual function test

Living and safety

Food stores

Separate stores for each diet, planned with you. See food.

Standard
FSSAI-labelled products
Life
Ready meals typically 12–24 months
Checks
Rotated before expiry

Medical kit and medicines

Trauma kit, each person's regular medicines and potassium iodide where a doctor prescribes it.

Standard
Planned with your doctor
Life
By expiry date
Checks
Rotated each year

Communications

Radios for official broadcasts in a shielded box, licensed two-way radio, internal intercom.

Standard
Licensed equipment only
Life
Many years
Checks
Tested in drills

Fire safety

Suitable extinguishers, detection and no open flames. Cooking is electric.

Standard
National Building Code of India 2016
Life
Extinguishers serviced yearly
Checks
Annual service

Lighting

LED lighting with a day and night cycle, emergency lights on separate batteries.

Standard
Low heat, low power
Life
10+ years
Checks
Emergency lights tested in drills

What the world follows

No single international shelter standard exists. These are the national systems engineers most often refer to, and the Indian codes we design to.

  • Switzerland

    The Federal Office for Civil Protection (BABS) issues the TWK 2017 technical guidelines for designing and building shelters, covering structure, air-tightness and loads. Shelter components such as ventilators and doors are type-approved. Switzerland has built shelter space for its whole population.

  • Finland

    The Rescue Act (379/2011) and its 2011 decrees require shelters in larger buildings. Standard S1 shelters have doors and valves rated to 1.0 bar, carry the collapse load of the building above, use NBC filtration with hand cranks, and must be inspected at least every 10 years.

  • United States

    UFC 3-340-02 sets methods for designing structures to resist explosions. FEMA P-361 covers tornado and hurricane safe rooms. Cold War public fallout shelters used a minimum protection factor of 40, far below what a modern private shelter targets.

  • Israel

    Since the 1990s, new homes have been required to include a reinforced protected room, a model for quickly reachable protection inside a building.

  • Filters, everywhere

    HEPA filters are classified under EN 1822 and ISO 29463. H13 and H14 classes are standard for shelters.

  • India

    There is no dedicated Indian standard for private shelters. We design to IS 456, IS 13920, IS 1893, IS 4991, IS 3370 and IS 6313 and the National Building Code 2016, follow NDMA guidance, and benchmark performance against the Swiss guidelines.

How long it takes

A typical Keep shelter on an accessible site, after approval. Larger, rocky, wet or remote sites take longer.

StageTypical durationNotes
Site assessment2–4 weeksSoil and groundwater tests, survey, approvals review
Design4–8 weeksStructural, life support, layout. Long-lead items ordered at the end of design.
Approvals1–6 monthsDepends entirely on the authority
Excavation and shoring3–8 weeksRock and high groundwater extend this
Raft and waterproofing2–4 weeks
Walls and roof6–12 weeksConcrete pours in stages, with curing time
Doors, valves, services4–8 weeksBlast doors and filters arrive 8–16 weeks after order
Backfill and earth cover2–4 weeksCompacted in layers
Fit-out3–6 weeksStores, finishes, cover function
Commissioning and drill2–4 weeksPressure test, filter test, full-load power and cooling

Overall: 4 to 6 months for a Haven, 6 to 9 for a Keep, 9 to 14 for a Citadel and 12 to 24 for an Estate, after approval. Remote mountain sites add seasonal limits. See retreat shelters.

Ask for the specification sheet for your site.

After the site assessment you receive a full component list, with the standard and rating for each part.