Components and standards
What goes into a shelter, part by part: what each component does, the standard it is built or tested to, how long it lasts and how long it takes to get. Then the standards the rest of the world uses, and how long a build takes.
Who checks what, and how oftenStructure
The shell that carries earth, resists blast and keeps water out.
Reinforced concrete shell
Walls 300–600 mm and roof slabs 400–750 mm of reinforced concrete, designed to carry earth cover, the collapse of structures above and blast overpressure.
- Standard
- IS 456, IS 13920 (ductile detailing), IS 1893 (seismic), IS 4991 (blast)
- Life
- Designed for 50+ years
- Checks
- Visual inspection for cracks and damp each year
Earth cover
1 to 3 metres of compacted fill over the roof. The cheapest and most effective radiation shield there is.
- Standard
- Compaction tested in layers during backfill
- Life
- Permanent
- Checks
- Settlement and drainage after each monsoon
Waterproofing system
Low-permeability concrete, external membranes, water-stops at every joint and sealed pipe sleeves. The system is chosen from the groundwater investigation.
- Standard
- IS 3370 principles for water-retaining concrete
- Life
- Membranes typically 20+ years
- Checks
- Sump levels and damp patches after monsoon
Sumps and twin pumps
Collect any water that reaches the structure and pump it out, on shelter power, with a standby pump.
- Standard
- Sized from site groundwater data
- Life
- Pumps 5–10 years
- Checks
- Test run every quarter
Anti-termite treatment
Soil treatment around the structure before backfill.
- Standard
- IS 6313
- Life
- Varies by treatment
- Checks
- Annual inspection
Doors and exits
Every opening is a weak point for blast, radiation and gas, so each one is engineered.
Blast door
A steel door in a steel frame cast into the concrete, rated to the shelter's design overpressure, with gas-tight seals and locking from inside.
- Standard
- Rated and tested to the shelter's blast class (1 to 3 bar+)
- Lead time
- 8–16 weeks, made to order
- Checks
- Seal and hinge service each year
Gas-tight inner door
Creates the airlock with the blast door, so people can enter and decontaminate without breaking the seal.
- Standard
- Air-tightness tested at commissioning
- Lead time
- 6–12 weeks
- Checks
- Seal inspection each year
Escape hatch and shaft
A second way out, placed outside any collapse zone, openable from inside and outside, concealed at the surface.
- Standard
- Same blast class as the main entry
- Lead time
- 8–12 weeks
- Checks
- Opened in every drill
Shielded entry passage
Entries that turn at right angles so there is no straight path for radiation, often with earth cover over the passage.
- Standard
- Designed into the structure
- Life
- Permanent
- Checks
- Kept clear of storage
Air
The system that decides how long a shelter can stay sealed.
NBC ventilation unit
Draws outside air through filters and pushes it into the shelter. Electric, with a hand crank for power failures.
- Standard
- Units type-tested for shelter use, such as Swiss-approved shelter ventilators
- Lead time
- 8–16 weeks, often imported
- Checks
- Run monthly, service each year
HEPA particle filter
Captures fallout dust, smoke, PM2.5 and biological particles. H13 captures at least 99.95% of the most penetrating particle size; H14 at least 99.995%.
- Standard
- EN 1822 / ISO 29463 filter classes
- Life
- Replaced on schedule, and after any use in contaminated air
- Checks
- Pressure drop each year
Gas filter (activated carbon)
Adsorbs chemical agents and many toxic gases. Kept sealed until needed.
- Standard
- Military and civil protection CBRN filter specifications
- Life
- Per manufacturer's shelf life; replaced after any exposure
- Checks
- Seal and date check each year
Blast valves
Fitted on every air intake and exhaust. They close in milliseconds when a pressure wave arrives, then reopen.
- Standard
- Shock-tested to the shelter's blast class
- Lead time
- 8–12 weeks
- Checks
- Movement test each year
Overpressure valves
Hold the shelter slightly above outside pressure so any leak flows outward.
- Standard
- Verified by pressure test at commissioning
- Lead time
- 6–10 weeks
- Checks
- Gauge reading in every drill
CO₂ scrubber and oxygen reserve
For recirculation mode when outside air is unusable, such as during nearby fires. Removes exhaled carbon dioxide; larger classes add oxygen reserve.
- Standard
- Sized to occupancy and hours of sealed operation
- Life
- Absorbent replaced by date or after use
- Checks
- Stock and date check each year
Monitoring
You cannot see radiation or smell carbon monoxide. Instruments do the noticing.
Radiation meters
A survey meter for dose rate inside and outside, plus personal dosimeters. They decide when it is safe to leave.
- Standard
- Calibrated instruments with certificates
- Life
- Many years with care
- Checks
- Calibration as the maker specifies, typically yearly
CO₂, CO and O₂ sensors
Alarm before air quality becomes dangerous. Carbon monoxide alarms are standard in every shelter.
- Standard
- Certified gas detectors
- Life
- Sensors typically 5–10 years
- Checks
- Test every drill, replace by date
Pressure, temperature and humidity
Confirms the overpressure is holding and the cooling is keeping up.
- Standard
- Read on a single panel
- Life
- 5–10 years
- Checks
- Logged in drills
Readiness monitoring
Optional remote alerts for water ingress, battery state and temperature, so faults are fixed long before an emergency.
- Standard
- Encrypted, minimal data
- Life
- Per device
- Checks
- Monthly status report
Power and cooling
In India, cooling is life support, so power is designed around it.
Battery storage
Lithium iron phosphate batteries take over instantly when the grid fails and carry the shelter for 48 hours or more on their own.
- Standard
- Certified cells and battery management, fire-rated enclosure
- Life
- Typically 10–15 years
- Checks
- State of health each quarter
Inverter and charge control
Converts and manages power from batteries, solar and generator, and sheds loads in priority order.
- Standard
- Certified to Indian electrical standards
- Life
- 10+ years
- Checks
- Annual service
Solar array
Concealed panels, or panels stored inside and deployed after an event.
- Standard
- BIS-certified modules
- Life
- 25+ years
- Checks
- Clean and test each year
Diesel generator and fuel
In a vented enclosure, with exhaust well away from the air intake and stabilised fuel.
- Standard
- Emission-compliant sets; fuel stored to safety rules
- Life
- Many years with servicing; fuel rotated
- Checks
- Run under load monthly
Cooling and dehumidification
Inverter cooling sized for full occupancy, with standby units on larger classes, and dehumidifiers to stop mould.
- Standard
- Sized to about 100 W of body heat per person plus equipment
- Life
- 10–15 years
- Checks
- Service before each summer
Water and sanitation
Stored water
Food-grade tanks inside the protected envelope, at least 4 litres per person per day plus reserve.
- Standard
- Food-grade materials; water to IS 10500
- Life
- Tanks 15+ years
- Checks
- Water rotated every 6–12 months
Purification
RO and UV purification, plus gravity filters that need no power.
- Standard
- Output tested against IS 10500
- Life
- Cartridges by schedule
- Checks
- Cartridge change each year
Protected borewell
For Estate and remote shelters, a well head inside or beside the protected envelope.
- Standard
- Subject to local groundwater rules
- Life
- Long term
- Checks
- Water quality test each year
Toilets and holding tank
Chemical toilets, or flushing toilets into a sealed tank with manual pump-out.
- Standard
- Sized to occupancy and days sealed
- Life
- 15+ years
- Checks
- Tested in drills
Backflow valves
On every drain, so a flooded or contaminated sewer cannot become a way in.
- Standard
- Fitted to all outgoing lines
- Life
- 10+ years
- Checks
- Annual function test
Living and safety
Food stores
Separate stores for each diet, planned with you. See food.
- Standard
- FSSAI-labelled products
- Life
- Ready meals typically 12–24 months
- Checks
- Rotated before expiry
Medical kit and medicines
Trauma kit, each person's regular medicines and potassium iodide where a doctor prescribes it.
- Standard
- Planned with your doctor
- Life
- By expiry date
- Checks
- Rotated each year
Communications
Radios for official broadcasts in a shielded box, licensed two-way radio, internal intercom.
- Standard
- Licensed equipment only
- Life
- Many years
- Checks
- Tested in drills
Fire safety
Suitable extinguishers, detection and no open flames. Cooking is electric.
- Standard
- National Building Code of India 2016
- Life
- Extinguishers serviced yearly
- Checks
- Annual service
Lighting
LED lighting with a day and night cycle, emergency lights on separate batteries.
- Standard
- Low heat, low power
- Life
- 10+ years
- Checks
- Emergency lights tested in drills
What the world follows
No single international shelter standard exists. These are the national systems engineers most often refer to, and the Indian codes we design to.
Switzerland
The Federal Office for Civil Protection (BABS) issues the TWK 2017 technical guidelines for designing and building shelters, covering structure, air-tightness and loads. Shelter components such as ventilators and doors are type-approved. Switzerland has built shelter space for its whole population.
Finland
The Rescue Act (379/2011) and its 2011 decrees require shelters in larger buildings. Standard S1 shelters have doors and valves rated to 1.0 bar, carry the collapse load of the building above, use NBC filtration with hand cranks, and must be inspected at least every 10 years.
United States
UFC 3-340-02 sets methods for designing structures to resist explosions. FEMA P-361 covers tornado and hurricane safe rooms. Cold War public fallout shelters used a minimum protection factor of 40, far below what a modern private shelter targets.
Israel
Since the 1990s, new homes have been required to include a reinforced protected room, a model for quickly reachable protection inside a building.
Filters, everywhere
HEPA filters are classified under EN 1822 and ISO 29463. H13 and H14 classes are standard for shelters.
India
There is no dedicated Indian standard for private shelters. We design to IS 456, IS 13920, IS 1893, IS 4991, IS 3370 and IS 6313 and the National Building Code 2016, follow NDMA guidance, and benchmark performance against the Swiss guidelines.
How long it takes
A typical Keep shelter on an accessible site, after approval. Larger, rocky, wet or remote sites take longer.
| Stage | Typical duration | Notes |
|---|---|---|
| Site assessment | 2–4 weeks | Soil and groundwater tests, survey, approvals review |
| Design | 4–8 weeks | Structural, life support, layout. Long-lead items ordered at the end of design. |
| Approvals | 1–6 months | Depends entirely on the authority |
| Excavation and shoring | 3–8 weeks | Rock and high groundwater extend this |
| Raft and waterproofing | 2–4 weeks | |
| Walls and roof | 6–12 weeks | Concrete pours in stages, with curing time |
| Doors, valves, services | 4–8 weeks | Blast doors and filters arrive 8–16 weeks after order |
| Backfill and earth cover | 2–4 weeks | Compacted in layers |
| Fit-out | 3–6 weeks | Stores, finishes, cover function |
| Commissioning and drill | 2–4 weeks | Pressure test, filter test, full-load power and cooling |
Overall: 4 to 6 months for a Haven, 6 to 9 for a Keep, 9 to 14 for a Citadel and 12 to 24 for an Estate, after approval. Remote mountain sites add seasonal limits. See retreat shelters.
Ask for the specification sheet for your site.
After the site assessment you receive a full component list, with the standard and rating for each part.